Within TRACE Project, 39 Deliverables are foreseen. These documents reflect the project results and outcomes and are written and reviewed by the project experts. As soon as the documents are officially released, the Public Deliverables (PU) as well as an executive summary of the Sensitive (SEN) ones will be provided on this section.

Deliverable No
Deliverable Name
Work Package 
Leader
Dissemination Level
Due Date (month)
D1.1
Quality Plan & Risk Management
WP1
NKUA
Sensitive
6
D1.2
Data Management Plan (A)
WP1
NKUA
Sensitive
6
D1.3
Data Management Plan (B)
WP1
NKUA
Sensitive
18
D1.4
Data Management Plan (C)
WP1
NKUA
Sensitive
36
D1.5
IPR Final Report
WP1
NKUA
Sensitive
36
D2.1
TRACE Technical Requirements (A)
WP2
AVLL
Public
15
D2.2
TRACE Technical Requirements (B)
WP2
AVLL
Public
30
D2.3
Ethics and Societal Report
WP2
ISIG
Public
30
D2.4
Ecosystem Development, Safety and Use Cases (A)
WP2
EPS
Public
15
D2.5
Ecosystem Development, Safety and Use Cases (B)
WP2
EPS
Public
30
D3.1
Report on reference architecture (A)
WP3
INTRA
Public
18
D3.3
TRACE platform (alpha release)
WP3
INTRA
Public
18
D3.4
TRACE platform (beta release)
WP3
INTRA
Public
36
D3.5
TRACE (final) platform release
WP3
INTRA
Public
36
D4.1
Infrastructural Elements of the TRACE Platform (A)
WP4
NKUA
Public
18
D4.2
Infrastructural Elements of the TRACE Platform (B)
WP4
NKUA
Public
36
D4.3
Synchromodal operations and optimization of shared resources (A)
WP4
UTH
Public
18
D4.4
Synchromodal operations and optimization of shared resources (B)
WP4
UTH
Public
36
D4.5
Security scheme and Visual interfaces (A)
WP4
CSEM
Public
18
D4.6
Security scheme and Visual interfaces (B)
WP4
CSEM
Public
36
D5.1
Barriers and Business opportunities (A)
WP5
INC
Public
18
D5.2
Barriers and Business opportunities (B)
WP5
INC
Public
36
D5.3
Regulatory Frameworks and Behavioural change (A)
WP5
EPS
Public
18
D5.4
Regulatory Frameworks and Behavioural change (B)
WP5
EPS
Public
36
D5.5
Socio-Economic Opportunities and Guidelines to Authorities
WP5
AVLL
Public
36
D6.1
Report on organisational readiness of the pilot setup (A)
WP6
TU WIEN
Public
18
D6.2
Report on organisational readiness of the pilot setup (B)
WP6
TU WIEN
Public
24
D6.3
Report on organisational readiness of the pilot setup (C)
WP6
TU WIEN
Public
36
D6.4
Report on trial period activities (A)
WP6
TU WIEN
Public
30
D6.5
Report on trial period activities (B)
WP6
TU WIEN
Public
36
D6.6
Report on formal assessment of trial periods
WP6
UM
Public
36
D6.7
Scenarios of Use Cases
WP6
TU WIEN
Public
36
D7.1
Commercialisation and Sustainability Options (A)
WP7
INC
Public
24
D7.2
Commercialisation and Sustainability Options (B)
WP7
INC
Public
36
D7.3
Dissemination & Communications Activities (A)
WP7
INC
Public
6
D7.4
Dissemination & Communications Activities (B)
WP7
INC
Public
24
D7.5
Dissemination & Communications Activities (C)
WP7
INC
Public
36
D7.6
Community building and Workshops
WP7
UNIMORE
Public
36